Starting the Dream
Contents
- 1 Starting the Dream
- 2 Breaking Ground
- 3 Early Foundation Work
- 4 First Day of Framing
- 5 Plumbing and Mechanical Work
- 6 Electrical Beginnings
- 7 Personal Milestones Alongside the Build
- 8 Water Connection
- 9 Painting and Early Finishes
- 10 Septic System Installation
- 11 Long Days and Humor on Site
- 12 Enjoying the Small Moments
- 13 Systems Coming Together
- 14 Final Months of the First Year
- 15 Celebrations Along the Way
- 16 Lessons Learned
- 17 Powering On
- 18 Reflections After One Year
- 19 Table: Year-One Milestones in Our Garage Apartment Build
In 2025, we bought six acres of wooded land. After more than 18 months of cleanup, site preparation, designing our house, and splitting the project into phases, we were finally ready to start.
The goal was simple but ambitious: build a debt-free, high-performance, addition-ready home.
Breaking Ground
On march 21st, 2025, we officially broke ground on our garage apartment. This was the start of countless nights and weekends of hard work, balanced alongside full-time jobs.
The first shovel into the earth marked the beginning of a journey we had been planning for years. We knew the work would be long and tough, but the dream of building a home with our own hands pushed us forward.
Early Foundation Work
We began with site excavation and footings. Anchoring, leveling, and preparing the ground were the first major steps.
Some unexpected moments added humor along the way, like when a frog decided the center footing was a perfect spot to take a bath.
We carved out stone, anchored bolts, and secured plates. Our slab was tarped over and watered daily, protecting it as it cured. There were lessons learned and challenges faced, but every small milestone moved the project closer to reality.
First Day of Framing
By July 2nd, 2022, the first day of framing arrived. Carefully laying out the structure square was critical. Each piece had to be precise, since this was the base that everything else would connect to.
We found a jib boom crane on a marketplace, which turned out to be an incredible help. Lifting heavy beams became manageable, and the process moved faster. Slowly, the walls rose, and the garage apartment began to take shape.

Plumbing and Mechanical Work
Alongside framing, the plumbing system started to come together. Our manifold would be mounted nearby, and we began installing pipe runs and fittings.
We tarped over the slab, watering it daily to help it cure, and we faced a few issues along the way — lessons that would stay with us as we moved forward.
Electrical Beginnings
Temporary power and lighting were essential to keep the work going into late evenings. A few inexpensive lights made it possible to work after dark, and the excitement of seeing the very first electric meter spin to life was unforgettable.
“Wait for it… we have power.”
Personal Milestones Alongside the Build
This project was more than construction — it became the backdrop of our lives.
- A marriage proposal: After six years together, the words came: “These have been the best six years of my life. Will you marry me?” The answer: “Yes.”
- Birthdays on site: Work didn’t stop for celebrations. On Alex’s 27th birthday, the day was still filled with measuring, cutting, and lifting.
These moments reminded us that building a home is about much more than materials — it’s about building a life.
Water Connection
Another major highlight was finally connecting water. The sound of it flowing for the first time was incredible.
“We got water. I’m stoked.”
It meant no more hauling water from elsewhere, and it symbolized another piece of independence falling into place.
Painting and Early Finishes
As framing and systems took shape, we reached the point where painting could begin. It was simple: two buckets, rollers, and patience.
Seeing fresh paint on the walls gave the project new life. It was the first time the garage apartment started to look less like a worksite and more like a livable space.
Septic System Installation
The next big task was the septic system. Finally, we could move on from paying for a portable toilet and invest in a long-term solution.
The key was to protect the topsoil and organic matter while installing the tank and lines. Solid-core pipes were laid out and connected. The system was tested and finalized: pipes designed to disperse wastewater into the septic bed.
“This clean-out here and this stub of pipe will be for our future house connection.”
With everything complete, the system worked exactly as it should. Another huge milestone was checked off the list.
Long Days and Humor on Site
Not every day was glamorous. Some days were spent bending fittings, tightening connections, and redoing parts that weren’t perfect the first time.
“Are you serious? I know, that’s what I just said.”
“It’s not tight enough. Oh, it’s not tight at all.”
There were mistakes, but there was also laughter. Dirty jokes, spilled water, fittings that had to be replaced for the fifth time — all of it became part of the journey.
Enjoying the Small Moments
Through the hard work, we made time to pause and enjoy life. Coffee breaks became a ritual, a reminder to slow down and appreciate the process.
“It’s good to take five minutes and enjoy a fresh cup of coffee every now and then. We only have one life to live, so soak it up.”
Even meals over an open fire turned into memories. “Don’t fall into the fire, that’s key,” one of us joked, while steam rose from the pot.
The project wasn’t just about construction — it was about living each moment to the fullest.
Systems Coming Together
Electrical panels were mounted, pipes were connected, and fittings tightened. Slowly but surely, everything found its place.
“Look at that panel — that’s beautiful.”
Each small success built confidence and momentum.
Final Months of the First Year
As the months rolled on, the site began to transform. What once was only dirt and brush now had structure, paint, plumbing, power, and systems that worked.
By late in the year, we installed final pipes, adjusted fittings, and completed finishing touches. There were setbacks — loose connections, leaks, and repeated adjustments — but every issue taught us something new.
The electrical meter was set, power flowed, and lights glowed for the first time. With temporary fixtures in place, the garage apartment felt alive.
Celebrations Along the Way
Milestones blended with personal life. Birthdays were celebrated on-site with work boots still on. Jokes were shared while tightening fittings. Meals cooked outdoors became rituals after long workdays.
It was during these ordinary moments that the extraordinary became clear: we weren’t just building a structure, we were building a home.
Lessons Learned
Mistakes happened, but they made us better builders. Every loose pipe, every misaligned fitting, every re-do gave us experience we couldn’t buy.
There were nights when exhaustion set in, but we learned to pause, laugh, and remind ourselves of the bigger goal: a debt-free, high-performance home, built by our own hands.
Powering On
The day power officially connected was unforgettable. Watching the electric meter spin up from zero was a reward for every hour of work poured into the project.
“We have power.”
With water and power both running, the apartment was finally functional.
Reflections After One Year
Looking back, the first year was filled with challenges, laughter, hard work, and unforgettable moments. From breaking ground to finishing paint, from water connection to electricity, every milestone built not only a home but also memories that will last forever.
“We’ve come a long way and still have a long way to go. Dream big and get to work, because life is short — and a year from now, you may wish you had started today.”
Table: Year-One Milestones in Our Garage Apartment Build
Stage | Description |
---|---|
Land Prep & Design | 18 months of cleanup and planning |
Breaking Ground | March 2022 — excavation begins |
Foundation & Slab | Footings, slab poured, cured daily |
Framing | First walls raised in July 2022 |
Plumbing & Water | Manifold set, water connection achieved |
Electrical Setup | Temporary lights, meter activated |
Septic System | Pipes installed, system tested |
Painting & Finishes | First layers of paint, protective coatings |
Final Months | Systems refined, fittings adjusted |
Reflections | One year of progress, lessons, and memories |